Rocking on…
The first stage of our work includes the placement of all rock into a so-called revetment all along Ports Creek and it has been progressing nicely: we are at over a quarter of rock works complete and earth embankment work will commence soon, moving to the next stage of building the embankment you can see in the above illustration.
Tweet, tweet, welcome home
Bird boxes installed
Our team have been busy the last few weeks installing a variety of bird boxes designed to support local wildlife. The bird boxes, which are manufactured in Germany, are perfect for sparrows, red starts, robins, wrens, starlings and many other bird species local to the area.
Design features include different size entrance holes to avoid competition between the birds, as well as ensuring that plenty of daylight is filtered in.
They also are large enough to provide overnight shelter for our feathered friends. We hope they enjoy their new homes!
Hilsea Lido update
Playtime!
You may have seen it from the road: there’s new play equipment at the park by Hilsea Lido!
The park is officially open now, so if you haven’t taken the kids there yet, go and check it out. As well as new equipment, there’s fresh sand and the area around the park has been tidied up too.
Essential SGN work on London Road
SGN have informed us they will be closing one lane southbound on London Road from Monday 3 March. This will be for two weeks, outside what used to be the News Centre building and then they will move further south for about three weeks to complete the work on this side of London Road.
The final phase of planned work by SGN, phase two, will start northbound from Monday 24 March for approximately 12 weeks.
Please plan your journey and use alternative routes where possible.
For more information
visit SGN’s website
If you have any questions or concerns regarding these works please contact SGN on 0800 912 1700




