Phase 1 – Anchorage Park – path improvement work underway

17.02.26

Anchorage park path improvement works 

As part of ongoing improvements to the North Portsea Coastal Scheme, work is taking place to upgrade the gravel path at Anchorage Park. These upgrades will create a smoother, higher‑quality route and ensure the coastal path remains in good condition as the wider scheme nears completion.

path at Anchorage Park

Key dates and activity

  • A small site compound has been set up within Anchorage Park, and this week sections of the path are being fenced off in preparation for the works.
  • 23 February – 28 April 2026:
    The main footpath works will take place and the path will be fully closed during this period.

    • A temporary parking suspension will be in place on part of Althorpe Drive to allow lorries to deliver materials to the compound.
    • Once deliveries are complete, the suspension will be lifted until the compound is removed at the end of the programme.
  • How the works will progress:
    Two teams will work along the path:

    • one moving west to east from the railway bridge
    • one moving east to west from near Eastern Road
      Completed sections will reopen as soon as they are ready.
      There will also be a short curing period (up to two weeks) where no visible activity takes place while the new surface hardens.
  • 1–8 May 2026:
    The site compound will be removed and the area fully cleared.

diversion map for path work at Anchorage park

We understand that closures are inconvenient, and we appreciate your patience. These improvements will help deliver a high‑quality, consistent coastal route as the 11‑year North Portsea Coastal Scheme approaches completion.