Phase 5 is the final phase of the North Portsea Coastal Scheme, running along the shoreline of Ports Creek in Hilsea. Construction began in September 2024 and is programmed to be completed in 2026.
This phase links seamlessly with the completed defences at Anchorage Park to the east and plays a key role in protecting homes, businesses, and infrastructure across the northern coast of Portsea Island.
As the area is known for its green open spaces, our work aims to retain and emphasize the natural feel. The embankment has been designed with sustainability in mind, using natural materials such as rock and soil and requiring very little concrete. Wherever possible, materials are being recycled and repurposed: nutrient-rich foreshore material excavated during construction has been carefully retained and added to the rock toe, supporting plant growth and habitat creation. Trees and vegetation that had to be removed are being reused to form marginal edging along the moat and contribute to other environmental enhancements – helping to preserve biodiversity and reduce waste throughout the project.
London Road temporary bridge (Portsbridge roundabout car park) is still in place. This temporary scaffold footpath has been provided to keep pedestrian access as short and safe as possible and to avoid a considerably longer diversion, including crossing London Road. While this does not remove the inconvenience, it is intended to reduce it as far as we reasonably can while work continues.
Please be assured that we will reopen the original footpath as soon as it is safe to do so.
Peronne Road temporary bridge has now been removed and is now fully reopened to the public.
Thank you in advance for your patience as we complete this final phase.
To minimise disruption and protect the natural environment, the construction site boundaries have been kept as close as possible to the footprint of the new embankment. This approach reduces the need to remove trees and shrubs, while maintaining maximum access for local residents and visitors throughout the works.
The entire southern side of the moat and Foxes Forest remains open and accessible during construction. The only closure is the small footbridge near the railway bridge, which is closed during the work to allow us to build the connection to the new footpath in that area.
The design for Phase 5 matches the successful approach used in Phase 1, combining raised earth embankments, a rock armour toe and enhanced footpaths. The design drawing show how the new defences integrate with existing features while improving public access and connectivity.
This phase includes a wide range of environmental improvements to support biodiversity and protect sensitive habitats along the moat, creek, and surrounding woodlands.
New funding secured for 2025/26 marks a major step forward for Foxes Forest and the historic Hilsea Lines Moat – an ecologically rich green corridor home to wetlands, reedbeds, and diverse wildlife.
As part of the North Portsea Coastal Scheme, this funding enables targeted restoration work to improve water quality and enhance the moat’s habitat and heritage.